Monitor costing systems on medium rise building or construction work Essay Example
- Category:Other
- Document type:Assignment
- Level:High School
- Page:1
- Words:681
Question 1
Use the old solution
Question 2
Amount ($) |
|
Preliminaries |
|
Groundworks |
|
Concrete |
|
Metalwork |
|
Hydraulics |
|
Electrical |
|
Mechanical |
|
Waterproofing |
|
Plasterer |
|
Carpenter Fitout |
|
Ceramic Tiler |
|
External Works |
|
3,524,700 |
Particulars |
Quantity |
Amount ($) |
|||
Preliminaries Consultant fees Authority and establishment Site clearing Site fence/hoardings Direct site labour Temporary services Builder’s Margin Total for Preliminaries |
|||||
Groundworks Service trenches, excavation, backfilling and leveling Total for Groundworks |
|||||
Concrete Concrete Basement 2 Concrete Basement 1 Concrete Level 1 Concrete Level 2 Concrete Level 3 Concrete Level 4 Concrete Level 5 Total for Concrete |
|||||
Masonry Basement 2 Masonry Basement 1 Masonry Level 1 Masonry Level 2 Masonry Level 3 Masonry Level 4 Masonry Level 5 Total for Masonry |
|||||
Metalwork Metalwork Basement 2 Metalwork Basement 1 Metalwork level 1 Windows and doors Metalwork level 2 Windows and Doors Metalwork level 3 Windows and Doors Metalwork level 4 Windows and Doors Metalwork level 5 Windows and Doors Metalwork level 1 fitout Metalwork level 2 fitout Metalwork level 3 fitout Metalwork level 4 fitout Metalwork level 5 fitout Total for Metalwork |
|||||
Hydraulics Hydraulics Rough in Sub basement Hydraulics Rough in Basement 2 Hydraulics Rough in Basement 1 Hydraulic Rough in Level 1 Hydraulic Rough in Level 2 Hydraulic Rough in Level 3 Hydraulic Rough in Level 4 Hydraulic Rough in Level 5 Hydraulics Fit off Basement 2 Hydraulics Fit off Basement 1 Hydraulic Fit off Level 1 Hydraulic Fit off Level 2 Hydraulic Fit off Level 3 Hydraulic Fit off Level 4 Hydraulic Fit off Level 5 Total for Hydraulic |
|||||
Electrical Electrical Rough in Below Basement Level Electrical Rough in Basement 2 Electrical Rough in Basement 1 Electrical Rough in Level 1 Electrical Rough in Level 2 Electrical Rough in Level 3 Electrical Rough in Level 4 Electrical Rough in Level 5 Electrical Fit off Basement 2 Electrical Fit off Basement 1 Electrical Fit off Level 1 Electrical Fit off Level 2 Electrical Fit off Level 3 Electrical Fit off Level 4 Electrical Fit off Level 5 Total for Electrical |
|||||
Mechanical Mechanical Rough in Lift Mechanical Fit off Lift Mechanical Rough in AC to Basement 2 Mechanical Rough in AC to Basement 1 Mechanical Rough in AC to Level 1 Mechanical Rough in AC to Level 2 Mechanical Rough in AC to Level 3 Mechanical Rough in AC to Level 4 Mechanical Rough in AC to Level 5 Mechanical Fit off Basement 2 Mechanical Fit off Basement 2 Mechanical Fit off to Level 1 Mechanical Fit off to Level 2 Mechanical Fit off to Level 3 Mechanical Fit off to Level 4 Mechanical Fit off to Level 5 Total for Mechanical |
|||||
Waterproofing Waterproofing to Level 1 Waterproofing to Level 2 Waterproofing to Level 3 Waterproofing to Level 4 Waterproofing to Level 5 Total for Waterproofing |
|||||
Range-hoods Cook-tops gas Kitchen sinks Laundry tubs Kitchens incl granite benchtops LDS white VC Vanities Misc. fittings Hardware and Joinery Total for PC Items |
|||||
Roof installation Total for Roofer |
|||||
Plasterer Plasterer to Basement 2 Plasterer to Basement 1 Plasterer to Level 1 Plasterer to Level 2 Plasterer to Level 3 Plasterer to Level 4 Plasterer to Level 5 Total for Plasterer |
|||||
Carpenter Fitout Carpenter Fitout to Basement 2 Carpenter Fitout to Basement 2 Carpenter Fitout to Level 1 Carpenter Fitout to Level 2 Carpenter Fitout to Level 3 Carpenter Fitout to Level 4 Carpenter Fitout to Level 5 Total for Carpenter Fitout |
|||||
Painter to Basement 2 Painter to Basement 1 Painter to Level 1 Painter to Level 2 Painter to Level 3 Painter to Level 4 Painter to Level 5 Total for Painter |
|||||
Ceramic Tiler Ceramic Tiler to Level 1 Ceramic Tiler to Level 2 Ceramic Tiler to Level 3 Ceramic Tiler to Level 4 Ceramic Tiler to Level 5 Total for Ceramic Tiler |
|||||
Carpet to Level 1 Carpet to Level 2 Carpet to Level 3 Carpet to Level 4 Carpet to Level 5 Total for Carpet |
|||||
Cleaner to Basement 2 Cleaner to Basement 1 Cleaner to Level 1 Cleaner to Level 2 Cleaner to Level 3 Cleaner to Level 4 Cleaner to Level 5 Total for Cleaner |
|||||
External Works All external work Total for External Work |
|||||
3,524,700 |