- Home
- Finance & Accounting
- building final claim certificate
Building final claim certificate Essay Example
- Category:Finance & Accounting
- Document type:Assignment
- Level:High School
- Page:1
- Words:150
Claim Reconciliation |
||||
Contract value (original) including PC items and Provisional Sums |
||||
Provisional Sums Expended |
Sub-total |
|||
PS 1 – Air Conditions |
14000.00 |
14000.00 |
14000.00 |
|
PS 2 – Sewer drain replacement |
||||
Total Provisional Sum adjustment |
$ 19,600.00 — |
|||
Prime Cost Items Purchased |
Sub-total |
|||
PC1 – Oven and Cooktop |
||||
PC2 – Wall Tiles |
||||
PC3 — Double glazed Windows |
||||
Plus Builder’s margin on Prime Cost Items |
||||
Total Prime Cost Item adjustment |
$ 18,300.00 — |
|||
Variations (approved) |
Sub-total |
|||
VO.1 Additional excavation and binding for footings |
||||
VO.2 Pergola over the rear deck |
||||
VO.3 Retaining wall to rear year |
||||
VO.4 Stain less steel Balustrading |
||||
Total variations |
$ 11,890 — |
|||
Interest on Late Payments |
Rate/Day |
Days Late |
Claim Value |
Interest applied |
Claim No.1. Painters claims for variation for the repaint work |
||||
Claim No. |
||||
Claim No. |
||||
Total Interest applied |
||||
Costs and Penalties applied |
Rate/Day |
Days Delay |
||
Liquidated Damages |
||||
Other penalties |
||||
Total Costs and Penalties applied |
||||
Final Contract Value |